What we supply
| Cross-section | Depth | Gauge | Typical job | |
|---|---|---|---|---|
| C purlin and girt | Channel with stiffening lips | 4″–12″ | 16, 14 or 12 | Roof purlins, wall girts, door and window headers |
| Z purlin and girt | Z shape | 4″–12″ | 16, 14 or 12 | Continuous runs that lap over each support |
| Hat channel | Shaped like a top hat | ⅞″–1½″ | 25 to 16 | Furring for walls and ceilings; metal over an old roof |
| Eave strut | C with a sloped top | About 7″–10″, and deeper | 14 or 12 | The roof-to-wall corner of a metal building |
| Square and rectangular tube | Closed hollow section | 2″–4″, and larger | 14, 12 or 11 | Carports, posts, trusses, gate frames |
| Stud and track | C stud seated in a U track | 1⅝″–6″, and deeper | 25 to 14 | Partitions, light bearing walls, soffit framing |
| Angle and flat bar | L or flat strip | Many sizes | Many gauges | Bracing, clips, trim backing |
| Beams and columns | Wide-flange or tube | Engineered | Engineered | Primary frames on bigger buildings |
Mills and makers each have their own size and coating lists; your quote names exactly what's coming.
What most light steel buildings are built from. They carry the roof, hold the wall panels and frame the doors.
The ends nest into the next piece over a support. That overlap makes the line stiffer and lets it span farther.
Gives you a straight, flat surface to fasten to. Used for re-roofing over shingles, for an air gap under panels and for furring out walls.
Equally strong in every direction, so it's the pick for posts, carports, trusses and gates.
Thin-wall framing for walls and ceilings inside.
Gauge and thickness
| Gauge | Roughly | Usually for |
|---|---|---|
| 20 | 0.033″–0.036″ | Light studs and hat channel |
| 16 | 0.054″–0.060″ | Lighter purlins and girts, bearing studs |
| 14 | 0.068″–0.075″ | Everyday purlins and girts, carports |
| 12 | 0.097″–0.105″ | Heavy purlins, eave strut, long spans |
The exact thickness shifts a little between standards and mills.
Finishes
- Galvanized. Normally G60 or G90. G90 has more zinc on it and resists rust longer.
- Primed. Red oxide or gray shop coat, for steel that will be painted later or stays indoors.
- Painted. Some members can come painted in the building color.
Engineering comes first
How deep, how heavy and how far apart all depend on the span, roof load, wind, snow and local code. On anything that needs a permit, the framing should be designed by a licensed engineer or come from stamped plans. We supply what the drawings specify, so send them along with the request.
Putting it together
- Screws, bolts or welds, whichever the design calls for.
- Laps, bracing and bridging go exactly as drawn. A purlin without its bracing is far weaker than its rating.
- Paint cut ends of galvanized steel with zinc-rich paint.
Questions we hear
C or Z?
The drawings decide. As a rule, C for short single spans and around openings, Z for long runs that overlap at the supports.
Will you cut to length?
Many members can be ordered that way. Put the lengths in your request.
Isn't steel pricier than lumber?
It often costs more at the start. It also lasts longer and won't burn, rot or feed termites.
Can I set a metal roof on hat channel over old shingles?
Often, yes. Check local code and the panel maker's instructions before you do.